West Virginia Record

Friday, September 20, 2019

Sunbelt Equipment Marketing alleges it is owed more than $300,000 for equipment used in Mountaineer Express project

State Court

By Carrie Bradon | Sep 3, 2019


MOUNDSVILLE – A Texas equipment rental company alleges it was not paid for the use of equipment needed in a major pipeline project.

Sunbelt Equipment Marketing Inc. filed a complaint in Marshall Circuit Court against Columbia Gas Transmission LLC, TransCanada USA Services Inc. and Welded Construction LP alleging breach of contract and unjust enrichment.

The suit states that the plaintiff provided equipment and machinery to Welded Construction for use on the Mountaineer Express Pipeline Project owned by Columbia and TransCanada. The plaintiff alleges Welded failed to pay it for $322,815.12 in invoices and it recorded a mechanic's lien.

The plaintiff is seeking all reasonable sums due, attorney fees and court costs. The plaintiff is represented by Charles R. Hughes of Bowles Rice in Charleston.

The case has been assigned to Judge Jeffrey Cramer.

Marshall Circuit Court case number 19-C-186

Want to get notified whenever we write about Marshall Circuit Court ?

Sign-up Next time we write about Marshall Circuit Court, we'll email you a link to the story. You may edit your settings or unsubscribe at any time.

Organizations in this Story

Marshall Circuit Court

More News